IA - N Melrose Drive Landslide
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Construction |
|---|---|
| Stage | active |
| Start | Oct 2026 |
| Completion | Feb 2027 |
| Budget | Not published |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:W03288 |
| Budget confidence | High |
| Bureau | WTR |
| Contact | Community Outreach Helpline 503-823-0102 |
| Current FY budget | 87000 |
| Description | This project will install approx. 115 feet of 6-inch ductile iron main, abandon approx. 115 feet of 6-inch ductile iron main and renew 2 services. |
| Design complete (est.) | 2026-09-30 |
| Design start (est.) | 2026-05-29 |
| Funding source | Cash |
| Geometry | line |
| Map pieces | 1 |
| Next FY request | 10000 |
| Previous FY budget | 104543 |
| Program | Distribution |
| Status detail | 040 Construction/Implementatio |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-12 | Routine | budget cut 100% ($102,000 -> $0) |
| 2026-07-29 | added | |
| 2026-07-29 | Routine | project added to the list |