Construction Project Update

IA - Broadway Corridor Onsite

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartMar 2025
CompletionOct 2026
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W03077
Budget confidenceHigh
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget36000
DescriptionThis project will install 1145-feet of 8-inch Earthquake Resistant Ductile Iron Water Main, 6 hydrants, and 4 one-inch services.
Design complete (est.)2025-04-22
Design start (est.)2024-06-07
Funding sourceCash
Geometrypt
Map pieces1
Previous FY budget229843
ProgramDistribution
Status detail040 Construction/Implementatio

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinebudget cut 100% ($466,135 -> $0)
2026-07-29Majorcompletion date slipped ~2 months