Construction Project Update

Grind & Pave - 6th Ave: Sheridan-Broadway, SW

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartSep 2025
CompletionSep 2025
Budget$125,000
CityPortland
SourcePortland CIP
Source IDportland_cip:T01276
BureauPDT
Current FY budget0
DescriptionImprove safety with lane re-org and wider bike lanes
Design complete (est.)2024-05-15
Design start (est.)2023-12-01
Geometryline
Map pieces1
Next FY request0
Source planCommunity Request, Paving List

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.