Construction Project Update

DS - S Kelly Ave North of S Macadam at DE

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartJun 2026
CompletionOct 2026
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W03278
Budget confidenceHigh
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget5000
DescriptionThis project will install approximately 65 feet of 4-inch DI Main. Install one service.
Design complete (est.)2026-06-30
Design start (est.)2026-03-27
Funding sourceCash
Geometryline
Map pieces1
Previous FY budget22497
ProgramDistribution
Status detail040 Construction/Implementatio

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinecompletion date slipped ~2 months
2026-07-29Majorconstruction started