Construction Project Update

DS - N Humboldt St W of Gay Ave

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Design
Stagedesign
StartDec 2026
CompletionApr 2027
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W03304
Budget confidenceLow
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget70000
DescriptionThis project will Install approx. 50 feet of 6-inch (DI) Ductile iron main. Install one (1) header service, install three (3) split services and one (1) hydrant.
Design complete (est.)2026-12-30
Design start (est.)2026-08-28
Funding sourceCash
Geometrypt
Map pieces1
Next FY request5000
Previous FY budget75000
ProgramDistribution
Status detail030 Design

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12added
2026-10-12Routinenew design-stage project appeared