StatusACTIVE · Predesign
Stageplanned
StartJun 2028
CompletionMar 2029
Budget$3,819,994
CityPortland
SourcePortland CIP
Source IDportland_cip:E11098
Budget confidenceLow
BureauBES
ContactCommunity Outreach Hotline 503-865-4300
DescriptionEliminate 5-year Sanitary Sewer Overflow (SSO) Risk within the Council Crest Sewer Basin and resolve mortality risk in an existing sanitary sewer pipe.
Design start (est.)2026-10-05
Geometrypoly
Map pieces1
ProgramT03 Maint & Reliability

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-09-14Notablestart date slipped ~5 weeks
2026-07-31Notablestart date slipped ~2 months