Alder Phase 2: 6th Ave and 10th Ave, SW

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartFeb 2026
CompletionOct 2026
Budget$1,528,883
CityPortland
SourcePortland CIP
Source IDportland_cip:T01339
BureauPDT
ContactMatt Kelly, 503-823-5831
Current FY budget0
DescriptionReplace temporary transit curb extension materials with concrete, install shelter footings for repurposed MAX shelter, replace streetlights, and install conduit.
Design complete (est.)2026-02-18
Design start (est.)2023-09-26
Geometryline
Map pieces1
Next FY request0
Source planRose Lanes/Enhanced Transit Corridor

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-10-12Routinecompletion date nudged 8 day(s)
2026-10-05Routinecompletion date nudged 11 day(s)
2026-09-04Notablecompletion date slipped ~4 weeks
2026-08-17Notablecompletion date slipped ~6 weeks