4th Ave: Lincoln - Burnside, SW

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartApr 2024
CompletionNov 2025
Budget$21,907,202
CityPortland
SourcePortland CIP
Source IDportland_cip:T00585
BureauPDT
ContactGabriel Graff, 503-823-5291, Gabriel.Graff@portlan
Current FY budget0
DescriptionThis project will reconstruct and repave SW 4th Avenue from SW Lincoln to SW Ankeny. A left-running protected bikeway and new signalized pedestrian crossings will be installed and ADA corner ramps wil
Design complete (est.)2023-04-10
Design start (est.)2019-12-05
Geometryline
Map pieces1
Next FY request0
ProgramFixing Our Streets

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-08-10Routinecompletion date nudged 13 day(s)