3260 SW Upper Dr North to 3139 Upper Dr

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Design
Stagedesign
StartFeb 2027
CompletionNov 2027
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W02396
Budget confidenceLow
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget5000
DescriptionThis project will install a total of 590 feet of new main. This includes installing 250 feet of 4-inch ductile iron (DI) main and 340 feet of 6-inch DI and abandoning approximately 285 feet of 2-inch
Design complete (est.)2027-02-08
Design start (est.)2019-02-05
Funding sourceBOND REIMBURSABLE
Geometryline
Map pieces1
Previous FY budget216064
ProgramDistribution
Status detail030 Design

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinebudget cut 100% ($327,745 -> $0)
2026-07-29Notablestart date slipped ~2 months