16th concrete separators, Johnson to Alder, NW

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartSep 2026
CompletionNov 2026
Budget$100,000
CityPortland
SourcePortland CIP
Source IDportland_cip:T01479
BureauPDT
Current FY budget0
DescriptionReplacing plastic separators with concrete separators.
Design complete (est.)2026-09-25
Design start (est.)2025-04-11
Geometryline
Map pieces1
Next FY request0

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-09-28Routinestart date nudged 9 day(s)
2026-09-14Notablestart date slipped ~5 weeks
2026-08-26Majorconstruction started
2026-08-17Notablecompletion date slipped ~2 months