16th concrete separators, Johnson to Alder, NW
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Construction |
|---|---|
| Stage | active |
| Start | Sep 2026 |
| Completion | Nov 2026 |
| Budget | $100,000 |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:T01479 |
| Bureau | PDT |
| Current FY budget | 0 |
| Description | Replacing plastic separators with concrete separators. |
| Design complete (est.) | 2026-09-25 |
| Design start (est.) | 2025-04-11 |
| Geometry | line |
| Map pieces | 1 |
| Next FY request | 0 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-09-28 | Routine | start date nudged 9 day(s) |
| 2026-09-14 | Notable | start date slipped ~5 weeks |
| 2026-08-26 | Major | construction started |
| 2026-08-17 | Notable | completion date slipped ~2 months |