Staff Restroom Improvements
Philadelphia · Philadelphia CPO
This city’s feed last changed on 2026-10-12. We check every morning.
| Status | Complete |
|---|---|
| Stage | complete |
| Completion | Jun 2025 |
| Budget | $34,613 |
| City | Philadelphia |
| Address | 2840 W DAUPHIN ST |
| Source | Philadelphia CPO |
| Source ID | philadelphia_cpo:14-25-4841-01|14012E|Staff Restroom Improvements|Resurfacing of facility's existing staff restrooms. |
| Actual completion | 2025-06-06 |
| Category | Public Health |
| Contact | [email protected] |
| Council district | 5 |
| Department | Department of Public Health |
| Estimated completion (as published) | Spring 2025 |
| Estimated cost (as published) | 34612.95 |
| Program page | https://www.phila.gov/departments/capital-program-office/ |
| Project coordinator | Mosley |
| Project number | 14-25-4841-01 |
| Scope | Resurfacing of facility's existing staff restrooms. |
| Site | Health Center 12 |
| Site code | 14012E |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
Nothing since we started tracking this project. We check every morning.