Sidewalk Replacement

Philadelphia · Philadelphia CPO

This city’s feed last changed on 2026-10-12. We check every morning.

StatusComplete
Stagecomplete
CompletionNov 2025
Budget$58,464
CityPhiladelphia
Address555 S 43RD ST
SourcePhiladelphia CPO
Source IDphiladelphia_cpo:14-20-4329-01|14003E|Sidewalk Replacement|Replacement of existing sidewalk along Chester Ave.
Actual completion2025-11-24
Archived05/24/2026
CategoryPublic Health
Contact[email protected]
Council district3
DepartmentDepartment of Public Health
Estimated completion (as published)Fall 2024
Estimated cost (as published)58464.4
Program pagehttps://www.phila.gov/departments/capital-program-office/
Project coordinatorDrosnock
Project number14-20-4329-01
ScopeReplacement of existing sidewalk along Chester Ave.
SiteHealth Center 3
Site code14003E

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.