Sidewalk Replacement
Philadelphia · Philadelphia CPO
This city’s feed last changed on 2026-10-12. We check every morning.
| Status | Complete |
|---|---|
| Stage | complete |
| Completion | Nov 2025 |
| Budget | $58,464 |
| City | Philadelphia |
| Address | 555 S 43RD ST |
| Source | Philadelphia CPO |
| Source ID | philadelphia_cpo:14-20-4329-01|14003E|Sidewalk Replacement|Replacement of existing sidewalk along Chester Ave. |
| Actual completion | 2025-11-24 |
| Archived | 05/24/2026 |
| Category | Public Health |
| Contact | [email protected] |
| Council district | 3 |
| Department | Department of Public Health |
| Estimated completion (as published) | Fall 2024 |
| Estimated cost (as published) | 58464.4 |
| Program page | https://www.phila.gov/departments/capital-program-office/ |
| Project coordinator | Drosnock |
| Project number | 14-20-4329-01 |
| Scope | Replacement of existing sidewalk along Chester Ave. |
| Site | Health Center 3 |
| Site code | 14003E |