Boiler Replacement

Philadelphia · Philadelphia CPO

This city’s feed last changed on 2026-10-12. We check every morning.

StatusComplete
Stagecomplete
CompletionSep 2027
Budget$773,000
CityPhiladelphia
Address2300 POPLAR ST
SourcePhiladelphia CPO
Source IDphiladelphia_cpo:14-26-4881-01|14160E|Boiler Replacement|Replacement of a 3000 MBH Steam Boiler and code compliance upgrades at the OFM Warehouse
CategoryPublic Health
Contact[email protected]
Council district5
DepartmentDepartment of Public Health
Estimated completion (as published)Fall 2027
Estimated cost (as published)773000
Program pagehttps://www.phila.gov/departments/capital-program-office/
Project coordinatorMosley
Project number14-26-4881-01
ScopeReplacement of a 3000 MBH Steam Boiler and code compliance upgrades at the OFM Warehouse
SiteFacilities Management Office Warehouse
Site code14160E

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Major24 projects: project marked complete