Twenty-Four Sycamores Public Restroom Building Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | Nov 2019 |
| Completion | Jul 2021 |
| Budget | $1,543,000 |
| City | New York |
| Address | FDR Drive, East 60th Street, East 61st Street, York Avenue |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:6599 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2021-07-01 |
| Construction completion (adjusted) | 2021-08-01 |
| Construction completion (projected) | 2021-05-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2018-09-01 |
| Design start | 2014-10-01 |
| FMS ID | 846 P-308SPCS |
| Funding source | City Council |
| Park ID | M108Q |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2019-06-01 |
| Procurement start | 2018-09-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the public restroom building at Twenty-Four Sycamores Park. |
| Total funding (as published) | $1,543,000 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
Nothing since we started tracking this project. We check every morning.