Statuscompleted
Stagecomplete
StartMar 2015
CompletionJun 2016
Budget$1,118,000
CityNew York
AddressFirst Avenue between East 41st Street and East 42nd Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:2324
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2016-06-01
Construction completion (projected)2016-06-01
Design % complete100.0
Design complete (actual)2014-03-01
Design start2009-03-01
FMS ID846 P-306TRYG
Funding sourceCity CouncilMayoral
Park IDM203A
Procurement % complete100.0
Procurement complete (actual)2015-01-01
Procurement start2014-03-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the sitting area at Trygve Lie Plaza.
Total funding (as published)$1,118,000