| Status | completed |
|---|---|
| Stage | complete |
| Start | Jul 2019 |
| Completion | Jul 2020 |
| Budget | $628,000 |
| City | New York |
| Address | West 81st Street and Central Park West |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:6413 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2020-07-01 |
| Construction completion (projected) | 2020-07-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2018-07-01 |
| Design start | 2017-07-01 |
| FMS ID | 846 P-307TRDR |
| Funding source | Borough President, City Council |
| Park ID | M053 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2019-06-01 |
| Procurement start | 2018-07-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct Bull Moose Dog Run in Theodore Roosevelt Park. |
| Total funding (as published) | $628,000 |