Statuscompleted
Stagecomplete
StartOct 2014
CompletionDec 2016
Budget$5,033,000
CityNew York
AddressRutherford Place, Nathan D. Perlman Place, East 15th Street, East 17th Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:2199
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2016-12-01
Construction completion (adjusted)2016-12-01
Construction completion (projected)2016-04-01
Design % complete100.0
Design complete (actual)2013-04-01
Design start2010-08-01
FMS ID846 P-302SSQP
Funding sourceBorough PresidentCity CouncilMayoral
Park IDM086
Procurement % complete100.0
Procurement complete (actual)2014-07-01
Procurement start2013-04-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the fence and sidewalks in the eastern half of Stuyvesant Square.
Total funding (as published)$5,033,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.