| Status | completed |
|---|---|
| Stage | complete |
| Start | Oct 2014 |
| Completion | Dec 2016 |
| Budget | $5,033,000 |
| City | New York |
| Address | Rutherford Place, Nathan D. Perlman Place, East 15th Street, East 17th Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:2199 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2016-12-01 |
| Construction completion (adjusted) | 2016-12-01 |
| Construction completion (projected) | 2016-04-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2013-04-01 |
| Design start | 2010-08-01 |
| FMS ID | 846 P-302SSQP |
| Funding source | Borough PresidentCity CouncilMayoral |
| Park ID | M086 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2014-07-01 |
| Procurement start | 2013-04-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the fence and sidewalks in the eastern half of Stuyvesant Square. |
| Total funding (as published) | $5,033,000 |