St. Vartan Park Playground Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | construction |
|---|---|
| Stage | active |
| Start | Mar 2026 |
| Completion | Mar 2027 |
| Budget | $4,797,000 |
| City | New York |
| Address | 1st Avenue between East 35th Street and East 36th Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:9248 |
| Borough | Manhattan |
| Construction % complete | 55.0 |
| Construction completion (projected) | 2027-03-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2023-04-01 |
| Design start | 2020-02-01 |
| FMS ID | 846 P-306STVA |
| Funding source | City CouncilMayoral |
| Park ID | M076 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2026-02-01 |
| Procurement start | 2023-04-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the playground in St. Vartan Park. |
| Total funding (as published) | $4,797,000 |