Seward Park Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartNov 2018
CompletionNov 2019
Budget$4,364,000
CityNew York
AddressEast Broadway, Canal Street, Essex Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:8566
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2019-11-01
Construction completion (projected)2019-11-01
Design % complete100.0
Design complete (actual)2017-12-01
Design start2016-11-01
FMS ID846 P-3PWBSEP
Funding sourceMayoral
Park IDM082
Procurement % complete100.0
Procurement complete (actual)2018-10-01
Procurement start2017-12-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the courtyard, gardens, paths, and fencing at Seward Park.
Total funding (as published)$4,364,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.