Construction Project Update

Sara D. Roosevelt Park Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statusdesign
Stagedesign
CityNew York
AddressEast Houston to Canal Streets between Chrystie and Forsyth Streets
SourceNYC Parks CIP
Source IDnyc_parks_cip:10358
BoroughManhattan
Construction % complete0.0
Design % complete100.0
Design complete (actual)2025-12-01
Design start2023-06-01
FMS ID846 P-3SARDRO
Funding sourceMayoral State
Park IDM105
Procurement % complete0.0
Project liaisonSteve Simon
SummaryThis project will reconstruct Sara D. Roosevelt Park.
Total funding (as published)Greater than $10 million

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.