Sara D. Roosevelt Park Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | design |
|---|---|
| Stage | design |
| City | New York |
| Address | East Houston to Canal Streets between Chrystie and Forsyth Streets |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:10358 |
| Borough | Manhattan |
| Construction % complete | 0.0 |
| Design % complete | 100.0 |
| Design complete (actual) | 2025-12-01 |
| Design start | 2023-06-01 |
| FMS ID | 846 P-3SARDRO |
| Funding source | Mayoral State |
| Park ID | M105 |
| Procurement % complete | 0.0 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct Sara D. Roosevelt Park. |
| Total funding (as published) | Greater than $10 million |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed