Riverside Park South West 69th Street Transfer Bridge Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | Jan 2025 |
| Completion | Jul 2026 |
| Budget | $8,636,000 |
| City | New York |
| Address | Hudson River at West 69th Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:1004 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2026-07-01 |
| Construction completion (projected) | 2026-04-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2019-05-01 |
| Design start | 2015-03-01 |
| FMS ID | 846 P-3W69SB2 |
| Funding source | FederalMayoralPrivate |
| Park ID | M353 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2024-10-01 |
| Procurement start | 2019-05-01 |
| Project liaison | Steve Simon |
| Summary | This project will stabilize and restore existing structures with historically appropriate materials at Riverside Park South. This project will also include adding lighting on gantry towers, providing |
| Total funding (as published) | $8,636,000 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-09-18 | Routine | budget cut 4% ($8,992,000 -> $8,636,000) |
| 2026-08-26 | Major | project marked complete |