Construction Project Update

Riverside Park South Playground, Bikeway, and Plazas Construction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartAug 2016
CompletionSep 2020
Budget$26,876,000
CityNew York
AddressRiverside Boulevard between West 62nd Street and West 70th Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:2368
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2020-09-01
Construction completion (adjusted)2020-09-01
Construction completion (projected)2018-08-01
Design % complete100.0
Design complete (actual)2015-01-01
Design start2013-05-01
FMS ID846 P-307RPKS
Funding sourceFederalMayoralPrivate
Park IDM353
Procurement % complete100.0
Procurement complete (actual)2016-06-01
Procurement start2015-01-01
Project liaisonSteve Simon
SummaryThis project will construct a portion of Riverside Park South between West 65th Street and West 68th Street, including new plazas, play areas, lawns, volleyball courts, and a dog run, and it will reco
Total funding (as published)$26,876,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.