Statusconstruction
Stageactive
StartOct 2026
CompletionOct 2027
Budget$309,000
CityNew York
AddressRiverside Park South at West 71st Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:10692
BoroughManhattan
Construction % complete0.0
Construction completion (projected)2027-10-01
Design % complete100.0
Design complete (actual)2025-06-01
Design start2024-06-01
FMS ID846 P-307RPAF
Funding sourceCity CouncilMayoral
Park IDM353
Procurement % complete100.0
Procurement complete (actual)2026-06-01
Procurement start2026-01-01
Project liaisonSteve Simon
SummaryThis Project will construct Adult Fitness Equipment in Riverside Park.
Total funding (as published)$309,000