Riverside Park 79th Street Boat Basin Dock A Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | May 2015 |
| Completion | Jun 2016 |
| Budget | $5,488,000 |
| City | New York |
| Address | Hudson River at West 79th Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:2363 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2016-06-01 |
| Construction completion (adjusted) | 2016-06-01 |
| Construction completion (projected) | 2016-05-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2014-03-01 |
| Design start | 2010-03-01 |
| FMS ID | 846 P-307R97D |
| Funding source | FederalMayoral |
| Park ID | M071 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2015-03-01 |
| Procurement start | 2014-03-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct Dock A at the 79th Street Boat Basin in Riverside Park. |
| Total funding (as published) | $5,488,000 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-09-18 | Routine | budget cut 0% ($5,489,000 -> $5,488,000) |