Statuscompleted
Stagecomplete
StartJul 2019
CompletionJul 2020
Budget$2,508,000
CityNew York
AddressMadison Street between Oliver Street and Catherine Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:8723
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2020-07-01
Construction completion (projected)2020-07-01
Design % complete100.0
Design complete (actual)2018-10-01
Design start2017-10-01
FMS ID846 P-3CPIPGI
Funding sourceMayoral
Park IDM196
Procurement % complete100.0
Procurement complete (actual)2019-04-01
Procurement start2018-10-01
Project liaisonSteve Simon
SummaryThis project will reconstruct Playground One.
Total funding (as published)$2,508,000