Peck Slip Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartJan 2020
CompletionJan 2021
Budget$5,388,000
CityNew York
AddressPeck Slip between Water Street and South Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:2165
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2021-01-01
Construction completion (projected)2021-01-01
Design % complete100.0
Design complete (actual)2019-05-01
Design start2017-12-01
FMS ID846 P-301PECK
Funding sourceFederalMayoral
Park IDM167
Procurement % complete100.0
Procurement complete (actual)2019-12-01
Procurement start2019-05-01
Project liaisonSteve Simon
SummaryThis project will reconstruct Peck Slip.
Total funding (as published)$5,388,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.