Mary O'Connor and Tudor Grove Playground Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | Nov 2022 |
| Completion | Aug 2023 |
| Budget | $1,000,000 |
| City | New York |
| Address | N/S East 42 Street & Tudor Place |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:9327 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2023-08-01 |
| Construction completion (projected) | 2023-11-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2020-02-01 |
| Design start | 2019-02-01 |
| FMS ID | 846 P-306TUDO |
| Funding source | City CouncilMayoral |
| Park ID | M203D, M203E |
| Park sites | 2 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2022-08-01 |
| Procurement start | 2020-02-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the play equipment and safety surfacing at Mary O'Connor and Tudor Grove playgrounds. |
| Total funding (as published) | $1,000,000 |