Manhattan General Site Work (MG-213M)
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | Jun 2015 |
| Completion | Dec 2016 |
| Budget | $1,059,000 |
| City | New York |
| Address | W. 52 St. To W. 54 St., 11 Ave. To 12 Ave. |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:6101 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2016-12-01 |
| Construction completion (projected) | 2016-12-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2014-06-01 |
| Design start | 2013-03-01 |
| FMS ID | 846 P-3PLG13B |
| Funding source | City Council |
| Park ID | M022, M277, M282, M354 |
| Park sites | 4 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2015-06-01 |
| Procurement start | 2014-06-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct pavements, fences, plantings, plumbing and general site work in Manhattan. |
| Total funding (as published) | $1,059,000 |