Little Flower Playground Synthetic Turf Field Construction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartMar 2020
CompletionSep 2020
Budget$531,000
CityNew York
SourceNYC Parks CIP
Source IDnyc_parks_cip:1202111
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2020-09-01
Construction completion (adjusted)2020-09-01
Construction completion (projected)2020-06-01
Design % complete100.0
Design complete (actual)2019-12-01
Design start2019-04-01
FMS ID846 P-3LGTURF
Funding sourceMayoral
Park IDM132
Procurement % complete100.0
Procurement complete (actual)2019-11-01
Procurement start2019-07-01
Project liaisonSteve Simon
SummaryThis project will construct a synthetic turf field at Little Flower Playground.
Total funding (as published)$531,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.