LaGuardia Corner Garden Fence Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | Sep 2019 |
| Completion | Jan 2020 |
| Budget | $379,000 |
| City | New York |
| Address | LaGuardia Place between Bleecker Street and West Houston Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:8923 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2020-01-01 |
| Construction completion (projected) | 2020-03-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2018-12-01 |
| Design start | 2018-04-01 |
| FMS ID | 846 P-3LGGRDN |
| Funding source | City CouncilMayoral |
| Park ID | MZ439 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2019-08-01 |
| Procurement start | 2018-12-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the perimeter fence at LaGuardia Corner Garden. |
| Total funding (as published) | $379,000 |