Construction Project Update

John Jay Park Sitting Area Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartSep 2021
CompletionMay 2022
Budget$632,000
CityNew York
AddressFDR Drive between East 76th Street and East 78th Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:7308
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2022-05-01
Construction completion (projected)2022-09-01
Design % complete100.0
Design complete (actual)2019-06-01
Design start2018-03-01
FMS ID846 P-308JJPK
Funding sourceCity Council
Park IDM045
Procurement % complete100.0
Procurement complete (actual)2021-04-01
Procurement start2019-06-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the sitting area at John Jay Park.
Total funding (as published)$632,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.