Henry M. Jackson Playground Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartAug 2016
CompletionJun 2017
Budget$1,691,000
CityNew York
AddressJackson, Madison, Henry Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:7031
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2017-06-01
Construction completion (projected)2017-08-01
Design % complete100.0
Design complete (actual)2016-01-01
Design start2015-01-01
FMS ID846 P-3CPIJAK
Funding sourceMayoral
Park IDM228
Procurement % complete100.0
Procurement complete (actual)2016-07-01
Procurement start2016-01-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the basketball and handball courts, planting, fencing and asphalt and concrete pavement at Henry M. Jackson Playground.
Total funding (as published)$1,691,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.