Hell's Kitchen Park Pavement Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartMar 2023
CompletionAug 2023
Budget$450,000
CityNew York
SourceNYC Parks CIP
Source IDnyc_parks_cip:1475111
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2023-08-01
Construction completion (projected)2023-12-01
Design % complete100.0
Design complete (actual)2022-10-01
Design start2022-05-01
FMS ID846 P-304HELK
Funding sourceCity Council
Park IDM277
Procurement % complete100.0
Procurement complete (actual)2022-09-01
Procurement start2022-05-01
Project liaisonCristin Leoutsakos
SummaryThis project will reconstruct pavement surfaces at the sports courts in Hell's Kitchen Park.
Total funding (as published)$450,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.