Hamilton Fish Park Playground Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | Jan 2025 |
| Completion | Jan 2026 |
| Budget | $3,644,000 |
| City | New York |
| Address | East Houston Street between Sheriff Street and Pitt Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:9856 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2026-01-01 |
| Construction completion (projected) | 2026-01-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2022-11-01 |
| Design start | 2021-06-01 |
| FMS ID | 846 P-303HMFS |
| Funding source | City Council |
| Park ID | M033 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2024-12-01 |
| Procurement start | 2022-11-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the playground at Hamilton Fish Park. |
| Total funding (as published) | $3,644,000 |