Construction Project Update

Hamilton Fish Park Basketball Courts and Adult Fitness Equipment Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartSep 2020
CompletionMay 2021
Budget$537,000
CityNew York
SourceNYC Parks CIP
Source IDnyc_parks_cip:1138111
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2021-05-01
Construction completion (adjusted)2021-06-01
Construction completion (projected)2020-12-01
Design % complete100.0
Design complete (actual)2020-03-01
Design start2018-11-01
FMS ID846 P-3HMFISH
Funding sourceBorough President, City Council
Park IDM033
Procurement % complete100.0
Procurement complete (actual)2020-02-01
Procurement start2019-09-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the basketball courts and adult fitness equipment at Hamilton Fish Park.
Total funding (as published)$537,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.