Glick Park Electrical Systems Reconstruction (Hurricane Sandy)

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartJun 2018
CompletionJun 2019
Budget$693,000
CityNew York
AddressEast River between East 36th and East 38th Streets
SourceNYC Parks CIP
Source IDnyc_parks_cip:6274
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2019-06-01
Construction completion (projected)2019-06-01
Design % complete100.0
Design complete (actual)2017-04-01
Design start2015-11-01
FMS ID846 SANDY3-17
Funding sourceFederalMayoral
Park IDM289
Procurement % complete100.0
Procurement complete (actual)2018-05-01
Procurement start2017-04-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the electrical systems at Glick Park due to damage from Hurricane Sandy.
Total funding (as published)$693,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.