East River Park East 6th Street Synthetic Turf Soccer Field & Running Track Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | Sep 2017 |
| Completion | Sep 2018 |
| Budget | $3,076,000 |
| City | New York |
| Address | East 6th Street and East River Park |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:6238 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2018-09-01 |
| Construction completion (projected) | 2018-09-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2016-11-01 |
| Design start | 2013-11-01 |
| FMS ID | 846 P-303ERSF |
| Funding source | Borough President, City Council |
| Park ID | M144 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2017-07-01 |
| Procurement start | 2016-11-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the synthetic turf soccer field and resurface the running track in East River Park. |
| Total funding (as published) | $3,076,000 |