Statusconstruction
Stageactive
StartApr 2026
CompletionApr 2028
Budget$85,183,000
CityNew York
AddressFDR, East River, East 59 & East 63 Streets
SourceNYC Parks CIP
Source IDnyc_parks_cip:9394
BoroughManhattan
Construction % complete12.5
Construction completion (projected)2028-04-01
Design % complete100.0
Design complete (actual)2024-10-01
Design start2019-02-01
FMS ID846 P-308ERP3
Funding sourceCity CouncilMayoral
Park IDM108Q1, M108T, M108T01
Park sites3
Procurement % complete100.0
Procurement complete (actual)2026-04-01
Procurement start2022-06-01
Project liaisonSteve Simon
SummaryThis project will stabilize and reconstruct portions of the East River Esplanade.
Total funding (as published)$85,183,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-09-18Routinebudget raised 0% ($85,182,000 -> $85,183,000)