East River Esplanade Seawall Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartAug 2025
CompletionSep 2025
CityNew York
SourceNYC Parks CIP
Source IDnyc_parks_cip:1931111
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2025-09-01
Construction completion (projected)2025-10-01
Design % complete100.0
Design complete (actual)2025-08-01
Design start2025-08-01
FMS ID846 P-6RETW23
Funding sourceMayoral
Park IDM108T
Procurement % complete100.0
Procurement complete (actual)2025-08-01
Project liaisonContact Us
SummaryThis project will reconstruct a seawall along the East River at East 70th Street along the East River Esplanade.
Total funding (as published)Less than $1 million

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.