| Status | completed |
|---|---|
| Stage | complete |
| Start | May 2021 |
| Completion | May 2022 |
| Budget | $1,859,000 |
| City | New York |
| Address | between the East River and FDR Drive, East 68th Street to East 70th Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:8633 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2022-05-01 |
| Construction completion (projected) | 2022-05-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2019-07-01 |
| Design start | 2017-05-01 |
| FMS ID | 846 P-308EREI |
| Funding source | City CouncilMayoral |
| Park ID | M108T |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2021-04-01 |
| Procurement start | 2019-07-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the East River Esplanade from East 68th Street to East 70th Street. |
| Total funding (as published) | $1,859,000 |