Dag Hammarskjold Plaza Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartJun 2024
CompletionAug 2025
Budget$1,869,000
CityNew York
AddressEast 47th Street between First Avenue and Second Avenue
SourceNYC Parks CIP
Source IDnyc_parks_cip:8628
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2025-08-01
Construction completion (adjusted)2025-10-01
Construction completion (projected)2025-06-01
Design % complete100.0
Design complete (actual)2022-09-01
Design start2017-05-01
FMS ID846 P-3DAGHAM
Funding sourceCity CouncilMayoral
Park IDM203C
Procurement % complete100.0
Procurement complete (actual)2023-12-01
Procurement start2022-09-01
Project liaisonSteve Simon
SummaryThis project will reconstruct Dag Hammarskjold Plaza including the fences, benches, pavements, trees, planting beds lighting for art stage lighting.
Total funding (as published)$1,869,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-09-18Routinebudget cut 0% ($1,870,000 -> $1,869,000)