Statuscompleted
Stagecomplete
StartFeb 2024
CompletionMar 2024
Budget$480,000
CityNew York
SourceNYC Parks CIP
Source IDnyc_parks_cip:1482111
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2024-03-01
Construction completion (projected)2024-04-01
Design % complete100.0
Design complete (actual)2023-06-01
Design start2022-08-01
FMS ID846 P-3STFCRL
Funding sourceMayoral
Park IDM017
Procurement % complete100.0
Procurement complete (actual)2023-06-01
Procurement start2022-10-01
Project liaisonCristin Leoutsakos
SummaryThis project will reconstruct the synthetic turf field at Corlears Hook Park.
Total funding (as published)$480,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.