Corlears Hook Park Dog Run Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | completed |
|---|---|
| Stage | complete |
| Start | Oct 2019 |
| Completion | Oct 2020 |
| Budget | $851,000 |
| City | New York |
| Address | Cherry Street, Jackson Street, FDR Drive |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:7309 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2020-10-01 |
| Construction completion (projected) | 2020-10-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2018-11-01 |
| Design start | 2017-10-01 |
| FMS ID | 846 P-303CRHP |
| Funding source | City CouncilMayoral |
| Park ID | M017 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2019-10-01 |
| Procurement start | 2018-11-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the dog run at Corlears Hook Park, adding stable ground surface, water features and dog waste containers, and replacing fencing. |
| Total funding (as published) | $851,000 |