Statuscompleted
Stagecomplete
StartNov 2025
CompletionAug 2026
Budget$2,862,000
CityNew York
Address348 East 54th Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:10564
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2026-08-01
Construction completion (projected)2026-08-01
Design % complete100.0
Design complete (actual)2024-01-01
Design start2022-07-01
FMS ID846 P-3CBHVAC
Funding sourceMayoral
Park IDM130
Procurement % complete100.0
Procurement complete (actual)2025-08-01
Procurement start2024-01-01
Project liaisonCristin Leoutsakos
SummaryThis project will reconstruct the HVAC systems at Constance Baker Motley Recreation Center.
Total funding (as published)$2,862,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-08-20Majorproject marked complete