Construction Project Update

Columbus Park Synthetic Turf Field Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartJun 2022
CompletionJul 2022
Budget$552,000
CityNew York
SourceNYC Parks CIP
Source IDnyc_parks_cip:1370111
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2022-07-01
Construction completion (projected)2022-07-01
Design % complete100.0
Design complete (actual)2022-04-01
Design start2021-07-01
FMS ID846 P-3COLUBT
Funding sourceMayoral
Park IDM015
Procurement % complete100.0
Procurement complete (actual)2022-04-01
Procurement start2021-09-01
Project liaisonCristin Leoutsakos
SummaryThis project will reconstruct the synthetic turf field at Columbus Park.
Total funding (as published)$552,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.