Construction Project Update

Collect Pond Park Construction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartAug 2011
CompletionNov 2013
Budget$7,516,000
CityNew York
AddressLafayette Street, Centre Street, Leonard Street, Franklin Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:2160
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2013-11-01
Construction completion (projected)2012-08-01
Design % complete100.0
Design complete (actual)2010-03-01
Design start2007-09-01
FMS ID846 P-301CPPK
Funding sourceFederalMayoral
Park IDM242
Procurement % complete100.0
Procurement complete (actual)2011-07-01
Procurement start2010-03-01
Project liaisonSteve Simon
SummaryThis project will expand Collect Pond Park into the adjacent parking lot and provide new plantings and a pond.
Total funding (as published)$7,516,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.