Clement Clarke Moore Park Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartJul 2018
CompletionJun 2019
Budget$1,338,000
CityNew York
Address10th Avenue between West 21st Street and West 22nd Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:7114
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2019-06-01
Construction completion (projected)2019-07-01
Design % complete100.0
Design complete (actual)2017-05-01
Design start2015-07-01
FMS ID846 P-304CCMP
Funding sourceCity CouncilMayoral
Park IDM257
Procurement % complete100.0
Procurement complete (actual)2018-04-01
Procurement start2017-05-01
Project liaisonSteve Simon
SummaryThis project will reconstruct Clement Clarke Moore Park.
Total funding (as published)$1,338,000