Citywide Pool Electrical Systems Reconstruction (CNYG-815MA)

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartOct 2016
CompletionJun 2019
Budget$1,729,000
CityNew York
AddressEast 76-East 78 Streets, Cherokee Place
SourceNYC Parks CIP
Source IDnyc_parks_cip:6585
BoroughStaten IslandQueensManhattanBronx
Construction % complete100.0
Construction completion (actual)2019-06-01
Construction completion (projected)2019-10-01
Design % complete100.0
Design complete (actual)2015-10-01
Design start2014-06-01
FMS ID846 P-6PDPLEL
Funding sourceMayoral
Park IDM045, M058, Q441, R109, R110, X034, X236
Park sites7
Procurement % complete100.0
Procurement complete (actual)2016-09-01
Procurement start2015-10-01
Project liaisonCristin Leoutsakos
SummaryThis project will reconstruct deteriorated electrical systems at various pool facilities citywide.
Total funding (as published)$1,729,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.