Statusdesign
Stagedesign
CityNew York
AddressEast Houston Street to Canal Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:6311
BoroughQueensBronxManhattan
Construction % complete0.0
Design % complete5.0
Design start2026-12-01
FMS ID846 P-6GASBSI
Funding sourceMayoral
Park IDM105, Q004, Q012, Q024, Q048, X092, X136
Park sites7
Procurement % complete0.0
Project liaisonCristin Leoutsakos
SummaryThis project will convert facilities to electric systems at various parks facilities citywide.
Total funding (as published)Between $3 million and $5 million

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-09-18Notableadvanced a phase (planned -> design)