Construction Project Update

Children's Magical Garden Water Service Construction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartJun 2022
CompletionSep 2022
Budget$151,000
CityNew York
AddressNorfolk Street and Stanton Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:9617
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2022-09-01
Construction completion (projected)2023-06-01
Design % complete100.0
Design complete (actual)2021-01-01
Design start2019-12-01
FMS ID846 P-3CMGWAT
Funding sourceCity Council
Park IDM396
Procurement % complete100.0
Procurement complete (actual)2022-03-01
Procurement start2021-01-01
Project liaisonSteve Simon
SummaryThis project will construct water service at Children's Magical Garden.
Total funding (as published)$151,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.